Data centre · Augsburg
Data centre
High-availability data centre: HVAC and plumbing design with redundant cooling and free cooling.
- Location
- Augsburg
- Period
- 2023
- Work stages
- LP 3 – 6
- Status
- Completed
- Client
- DVT Consulting AG
- MEP volume
- 12,3 Mio. EUR
Project description
Data centre, Augsburg
For a data centre in Augsburg we designed and detailed the heating, air conditioning, ventilation and plumbing systems. The core is a redundant cooling concept (N+1) with free cooling that minimises the energy demand of IT cooling for most of the year.
The plant is designed for high availability and maintenance-friendly operation. Work stages 3 to 6 were completed in 2023.